Monte Carlo simulation

Running a model many times with its inputs drawn at random from their ranges, to see the spread of outcomes rather than one estimate. Where P50 and P90 come from when the inputs are uncertain.

How it works

Each uncertain input gets a probability distribution instead of a single value. Annual irradiance might be normal, with a mean and a standard deviation. Capital cost might be triangular, with a low, a likely and a high value. The model draws one value for each input, runs, and records the outputs, such as energy, IRR or minimum DSCR. It repeats this thousands of times. Sorting the results gives their distribution. The median run is the P50, and the value exceeded in 90% of runs is the P90.

Material relationships between inputs should be preserved when sampling. Low wind can come with high prices, partly offsetting lost generation revenue; a construction delay can come with higher cost, compounding the downside. Ignoring these relationships can overstate or understate risk. The sampling error of a percentile falls with the square root of the number of runs N, so going from 2,500 runs to 10,000 halves it. The results can be no better than the input ranges. A simulation built on guessed ranges gives precise-looking numbers with little behind them.

Why it matters

Projects face many uncertainties at once, and the worst outcomes come when several go wrong together. Monte Carlo shows how likely those combinations are. Lenders use the low percentiles to size debt and set reserve accounts. Developers use the spread to price risk into a bid or to decide how much revenue to hedge. For a merchant plant or a battery, whose revenue depends on the path prices take, it is often the only practical way to see the downside.

A worked example

A solar plant's annual energy is drawn from a normal distribution with mean 220,000 MWh and standard deviation 5%. Its average captured price is drawn with mean $45/MWh and standard deviation $8/MWh. One run might draw 209,000 MWh and $41/MWh, giving 209,000 × 41 = $8.57 million of revenue. After 10,000 runs the results are sorted from highest to lowest. The 5,000th is the P50, close to $9.9 million. The 9,000th is the P90, close to $7.6 million.

Illustrative figures.